Page image

D.-7

1894. NEW ZEALAND.

MILBURN LIME AND CEMENT COMPANY (LIMITED) (REPORT OF R.L. MESTAYER, Esq., M.Inst.C.E., ON CERTAIN PARCELS OF CEMENT SUPPLIED TO THE GOVERNMENT BY THE).

Laid on the Table by the Hon. Mr. Seddon, with the leave of the House.

Drainage Engineer's Department, Wellington, Ist October, 1894. Sic, — Ec the Milium Cement. I have the honour to report as follows on the several parcels of this cement delivered to the Government, and which I was directed by you to examine : — On the 27th August last I met Mr. Wilson, 0.8., representing your department, and Mr. Woodhead, representing the Milburn Cement Company, at the railway-yard, Pipitea, and took samples from four parcels of cement. In selecting the samples, six bags were taken from each lot, and an equal quantity of cement from each bag was put into a wooden box, which was vailed and sealed up in my presence ; the boxes were then, sent to the Corporation yard, at Clyde Quay, and remained there unopened until I could be present. Each box was marked according to the parcel from which the sample had been taken, the marks being as follows : — Ml: From a parcel of 462 bags in the carpenter's shop, delivered on the 30th April last. M 2 : From a parcel of 180 bags, also in the carpenter's shop, delivered on the 26th June last. M 3 : From a parcel of 300 bags in the Permanent-way Store, delivered on the 11th June last. M 4 : From a parcel of 180 bags, also in the Permanent-way Store, delivered on the 16th June last. A summary of the results of the various tests is given in Table A, and in Table B are given the results in full of the tests for tensile strength. The methods of procedure were as follows: — Eight pats of neat cement were gauged with 21 per cent, of water on the Bth September; they were marked Ml, M 2, M 3, M 4, two being taken from each sample. They were allowed to set for twenty-four hours in air, and then one of each pair was immersed in water, and left there until last Friday ; the remaining four were kept in air. I send herewith the eight pats, and have marked those that were kept in water with a " W," in addition to the sample-marks before described. No signs of cracking or distortion are perceptible in any of the parts; those kept under water were all attached to the glass when taken out of the water, those kept in air were all loose on the glass within two days after setting. For tensile strength twelve briquettes were prepared from each sample; three of each were broken at each trial. The trials were made when the briquettes were three, seven, fourteen, and twenty-one days old. The briquettes were prepared on a slab of glass, the cement being well worked and rammed into the moulds to insure absence of air-bubbles, and allowed to remain in the air for twenty-four hours; they were then immersed in water until they were removed to the testing-machine. The briquettes are 1 square inch in section at the centre, and were broken in a Bailey's cementtesting machine, the weight being obtained from water flowing into a receiver attached to the lever of the machine. All the briquettes broke fairly through the centre, and appear to have yielded to a direct strain only, as there is a total absence of splintering or of diagonal fracture which invariably accompanies any cross strains. In Table A is given the mean result of all the tests. All the samples stood the 3001b. per square inch at seven days, and, with one exception, they showed a marked increase in strength at fourteen and twenty-one days; the exception is sample M 2, which gives a mean strength of 4431b. at seven days and only 4401b. at fourteen days, recovering, however, during the succeeding fortnight, and giving a result slightly better than that for Ml at the twenty-eight-day test. I could not detect any difference in the rate of settling of the parts ; all the samples set very slowly, and could be easily marked with the thumb-nail twenty-four hours after gauging. Judging from the results of the tensile tests, it appears that the samples M 2 and M 3 set rather more quickly than the others, but for all practical purposes there is very little difference between the four. In addition to the tests of neat cement, I had some briquettes made of three parts of sand to one part of cement; some of these were allowed to set and dry in air, others were kept in air for twenty-four hours and then immersed in water until tested. At seven days those kept under water broke at less than 401b. per square inch. At seven days those kept in the air broke at less than 701b. per square inch. Similar briquettes made with sand and Portland cement stood from 1121b. to 1681b. at seven days when kept under water.

Log in or create a Papers Past website account

Use your Papers Past website account to correct newspaper text.

By creating and using this account you agree to our terms of use.

Log in with RealMe®

If you’ve used a RealMe login somewhere else, you can use it here too. If you don’t already have a username and password, just click Log in and you can choose to create one.


Log in again to continue your work

Your session has expired.

Log in again with RealMe®


Alert