Page image

19

1.—2 D

Dobson, officially in May, 1866, a copy of which report was sent to us?— Yes; I had learned that in Mr. Montgomery. 1868. I have not seen the report. -— 239. Are you aware that from that day to this we have never ceased to make the claim, that it was 8 JNor '' lB7r continually renewed, and increased as the work went on ?—You kept on renewing it, but I do not think you made it until some years alter the work had been commenced. 240. Are you aware that in 1867, while this dispute was going on, we were called upon to send in tenders for tbe supply of some of this samo material in a different place to that in which we were placing it, to place it in a certain direction altogether beyond the line of our original contract?—l believe there was such a contract entered into, and it was carried out. 241. Are you aware that the price we were paid was one shilling a yard higher than this claim because there was a little extra haulage I —l am not aware of that.

Monday, 3rd December, 1877. Mr. E. Dobson, C.E., examined. jf r Dohon 242. The Chairman.] You were engineer for tbe Lyttelton Bailway contract ?—Yes. 243. When the petitioners had the contract for its construction ?—Yes. 344. The original contract was for £24,000 ?—Yes; that was the amount of Holmes and Company* contract. 245. Before that was completed, we understand there was a deviation from the original contract? — Yea ; the deviation of tbe tunnel was altered. 246. When was that agreed to by tbe contracting parties?—l think it must have been at the end of 1862. I could not say exactly unless I referred to the papers. 247. What was the nature of the deviation?—lt was to make tho tunnel straight instead of curved. The alterations were all at the Lyttelton end. 248. Had anything been done at the Lyttelton end when this deviation was made ?—The drives had been begun. The heading had been driven on the curves. 249. That work was done away with ; it was lost?— Yes. 250. Was tbe agreement for this deviation reduced to writing ?—No; tbe contractors expressed willingness to make the alteration, and do all that was necessary, for a sum of £5,000. The Executive gave me verbal instructions to get tbe alterations made, and a vote for £5,000 was taken in the Provincial Council. 251. What was to be done for the £5,000 ? —lt was to include the whole cost of altering the tunnel. 252. Did it refer to tbe tunnel only ?—To nothing else I believe. 253. It was extra work?—l should not call it extra work ; I should call it alterations. 254. Could you give us a detailed statement of the work done?—No ; not without having my working plans before me. It was a a very complicated work ; there were two water courses and three public roads to be dealt with. 255. In the plan before tbe Committee, it appears that under tho original contract, some reclamation was to be made seaward of the tunnel mouth ?—Yes ; that portion marked red in pencil. 256. This sea wall (on the face of the embankment) was to be of stone taken from the tunnel?—lt was not a sea wall at all; it wa3 simply an embankment. That is to say there was no masonry ; it wa9 simply rubble stone thrown into the sea. 257. Could you tell the committee how many cubic yards of stone it involved?—No; not without the plans; the quantities were all carefully taken out on them. 258. It appears to be about 30,000 cubic yards to me by tbe section of the work ; could you say approximately ?—No. 259. What was to fill in this land which was to be reclaimed?— Partly tbe stuff out of the tunnel and partly the stuff from the excavation near the mouth. 260. The filling up had to be done by the contractors ?—Yes. 261. After the alteration was decided upon, the original line of embankment was extended further seaward ? —Yes ; They tipped tbe stone all along the outer line shown on the plan. 262. Supposing the original contract had been carried out, the line of reclamation would have been thus shown on tbe plan, and marked red in pencil ?—Yes. 263. What would then have been done with tbe surplus stone?— That was a question for tbe contractor entirely ;he would do what be pleased with it. The contract was drawn in such a way as to relieve the Government of any expense in connection with the surplus. If it had turned out bad the Government might, unless such a provision were inserted, have been put to many thousands of pounds expense; therefore I specially guarded the Governmant against that contingency. Of course, if it were hard rock it would have been good to the contractor, although there would have been the expense of cutting through it. 264. Was there no agreement as to the land tbe spoil was to bo put upon ?—The Government were bound to find land when required by tbe contractors, but the contractors were bound to pay for the cost of such bind. 265. Supposing tbe contractors had selected land to the east of the reclaimed land, what then ?— Tho Government would not have allowed them to take that land, at any rate not tho freehold of it. 20(5. Where would they have found land ?—That Ido not know ; it had nothing to do with us. That was matter entirely resting with tbe contractor. 267. What was the number of cubic yards between the first reclamation and the second1? —I could not say exactly. When 1 reported, it was about 30,000 cubic yards, but 1 believe there has been more added since then ; 30,000 was the quantity I thought necessary to give a proper curve. Originally my idea was to make the station in a straight line from tbe tunnel. 268. Where is tbe present line of reclamation I —Seaward of the original line as shown on plan. It was estimated that the quantity to be filled in would be 30,000 yards additional.

Log in or create a Papers Past website account

Use your Papers Past website account to correct newspaper text.

By creating and using this account you agree to our terms of use.

Log in with RealMe®

If you’ve used a RealMe login somewhere else, you can use it here too. If you don’t already have a username and password, just click Log in and you can choose to create one.


Log in again to continue your work

Your session has expired.

Log in again with RealMe®


Alert