PROGRESS AT ARAPUNI.

BUILDING STAFF HOUSES.

ROAD i DEVIATION . WORK.'

[BY TELEGRAPH.—OWN CORRESPONDENT.] ;'•" , MORHINSVILI/E. Monday. The first of the' permanent residences at "Arapuni is ■ now;nearing completion.' It will be the resident engineer's home, : and should' be ready for; occupation in a few days- Two more houses at Arapuni-, will be built immediately. ;, '. ■ " X The construction of the road deviation round Pearson's j Hill .is proceeding ,as weather conditions permit, and it is understood; that the plans for the. projected continuation of 'this road to : apunl along the eastern bank - of the ' Waikato .River gorge are now completed. i , '.' ; V The Public Works Department, it is reported, is also" forthwith undertaking the: re-conditioning of the Waipa Bridge, "on the Horahora Road, to permit of heavy traffic between ■ Horahora and Arapuni. ,; i; -

This article text was automatically generated and may include errors. View the full page to see article in its original form.
Permanent link to this item

https://paperspast.natlib.govt.nz/newspapers/NZH19230807.2.46

Bibliographic details

New Zealand Herald, Volume LX, Issue 18471, 7 August 1923, Page 6

Word Count
130

PROGRESS AT ARAPUNI. New Zealand Herald, Volume LX, Issue 18471, 7 August 1923, Page 6

PROGRESS AT ARAPUNI. New Zealand Herald, Volume LX, Issue 18471, 7 August 1923, Page 6