ARAPUNI WORKS.

COMPLETION DELAYED BY FLOOD. (BY TELEGRAPH PBEBB ASSOCIATION.) HAMILTON, Jan. 28. The flooding of the foundations of the power-house site at Arapuni hydroelectric works through the river breaking through during the October floods, will mean a delay in the completion of the main scheme. The three-year contract expires next August, but an extension of time for probably six-months will be sought. Other work in connection with this big undertaking is well advanced.