Rain Delays Diversion
(N.Z. Press Association)
ROTORUA, Nov. 21
The Matahina Dam diversion tunnel closure, planned for tomorrow, has been deferred a day because of the high level of the Rangitaiki river.
Mr J. J. Chesterman, power engineer for the £l5 million Matahina project, said it was now hoped to close the tunnel on Wednesday morning.
Permanent link to this item
https://paperspast.natlib.govt.nz/newspapers/CHP19661122.2.28
Bibliographic details
Press, Volume CVI, Issue 31223, 22 November 1966, Page 3
Word Count
56Rain Delays Diversion Press, Volume CVI, Issue 31223, 22 November 1966, Page 3
Using This Item
Stuff Ltd is the copyright owner for the Press. You can reproduce in-copyright material from this newspaper for non-commercial use under a Creative Commons BY-NC-SA 3.0 New Zealand licence. This newspaper is not available for commercial use without the consent of Stuff Ltd. For advice on reproduction of out-of-copyright material from this newspaper, please refer to the Copyright guide.
Acknowledgements
This newspaper was digitised in partnership with Christchurch City Libraries.